3/17/2025
Article 16: Technical installation in progress
The beginning of March sees the construction site resume after the February break. We start with the electrical conduits – laying the paths for the home’s electrical system. The sheaths will allow the wires to be passed correctly once the structure is in place.
At the same time, the first major deliveries are arriving: 7 cubic meters of sand for the interior coatings and the 32 solar panels which will provide our electricity.