8/31/2025
Article 24: Smoothing and installation of panels
August was a busy month. We were finally able to install our swisspanels (the steel sheets) on which we attach the solar panels. To date, almost all of our 32 panels are in place; There are only 4 left to ask next Friday. It takes a little time but it’s not too difficult.
At the same time, we continue to install the lime coating. This week was a big week: we attacked the “body coating” from Wednesday to Saturday. This is the substantial layer that fills in the gaps and provides the basic texture. We still have next week to finish this layer before starting the finishing.