6/28/2025

Article 20: The cork and the countdown

At the end of June, the preparation of the facades comes to an end. This week, we installed the cork boards at the bottom of the walls. It’s done !

We still have one last primer coat (HAGA 305) to apply and a few small details to sort out next week. But the schedule is now clear: we will start throwing lime on the straw the week of July 9. The goal is to be ready on time.